Pile Driving

phase 1: July 29th – August 9th     20 test piles will be driven to verify correct length to sub-surface bearing layer. Expected duration of driving is 2-3 days depending on actual localized subsurface conditions.

phase 2: August 26th  - September 20th  The remaining 60 piles will be delivered and driven. Expected duration of pile driving is 3 to 5 days depending on actual localized subsurface conditions. 

*The remaining phase 2 pile driving will be completed by September 11th. Foundation work will continue through October 2019.