Pile Driving: phase 1


20 test piles will be driven to verify correct length to sub-surface bearing layer. Expected duration of driving is 2 days depending on actual localized subsurface conditions.

Update: Crane body will be here Thursday late morning. Monday 8/5 they will be delivering the crane booms and assembling the booms and counter weights on the Crane. Tuesday 8/6 drive test piles and Dynamic testing. Baring any setbacks the first 20 piles will be completed on Wednesday 8/7 .

Update: Weather has caused pile driving to continue into Friday 8/9.

Earlier Event: July 25
Earthwork for piles and foundations
Later Event: August 5
Foundation