Demolition Narrative for 1/18/2019

An update on the construction progress for the Old Library 1/18/2019.

Demolition continued this week as crews make their way towards Cayuga St. Much of the visible structure is down. Debris is wetted down before loading into sealed trucks. Trucks are sprayed down in the decontamination area just inside the gates. Colder temperatures have caused the spray to encapsulate much of the debris in a layer of ice. Gorick was off-site on Tuesday (1/15/2019) to complete mandatory annual hazmat training. The Tuesday prior (1/8/2019) Gorick was off-site to complete mandatory annual asbestos training. No demolition activity occurred on those days.

Some updates to scheduled activity for the week of 1/21/19.

  • Monday- No demolition work due to impending storm and predicted low temperatures. (Snow removal may occur)

  • Tuesday- Tentative due to storm and predicted low temperatures. (Snow removal may occur)

  • Wednesday thru Friday- Resume demolition of the remainder of the building and continue hauling debris to the disposal site.

All air monitors continue to run properly and to date no exceedances have been noted. Click the button to see a copy of the Air Quality Monitoring Reports.

Please continue to check the www.libraryplaceconstruction.com website for updates.  