Demolition Narrative for 3/21/2019

Here is an update on the demolition, as we move towards the construction phase we will continue to update as information becomes available. 

We re-surveyed the condition of the existing column footers vs. the as-built drawings and found that eight of the column footers were not where indicated on the as-builts. Since this creates a conflict with portions of the new structure, these column footers are being removed. 

According to LeChase Construction Services, the hammering associated with this removal will be complete by the end of the day tomorrow (Friday 3/21), and Gorick will be fully demobilized by next Tuesday 3/26.

Remaining intact on the site: a portion of the bus garage retaining wall along the west property line to support the Life Long parking lot.  

Please continue to check the www.libraryplaceconstruction.com website for updates.  