Demolition Narrative for 12/28/2018

Demolition continued on the North side of the library this week. Water is being applied using a high pressured water mister, with between 4,000-8,000 gallons of water used daily. NYS Department of Labor was onsite 12/27/2018 and observed correct working practices. The Cat 321 excavator was moved off-site after it was completely pressure washed clean, and the Cat 345 excavator was mobilized on site. Site was secured for the long weekend with no work scheduled 12/31/18 or 1/1/19. Set to resume Demolition starting Wednesday 1/2/19.